Tuesday 14 May 2013

Still waiting

No work on site for just over a week now. The brickies may be back later this week to do the remaining ground floor brickwork but nothing else can be done until the power lines issue is resolved. There is a good chance that the power company will be assessing the site next week. Interestingly, the CM now thinks he may have spoken prematurely when he said that Comdain will pay for these additional works. Not sure how we feel about footing the bill for something that one would expect (quite reasonably) an experienced builder to have foreseen. We will have to wait and see how this all turns out.